Road Construction

pavingThis project is for road construction on the following streets:

  • Sundance Court
        (All of Sundance Court to be
         completed)
  • Trophy Club Drive
         (Southbound Side Only from
         Durango Drive to Bobcat Blvd)
  • Meadowbrook Lane
         (Street from 10 - 15 Meadowbrook Lane
         Only to be completed)

This project road construction includes:

  • Pavement removal
  • Road reconstruction
  • Storm drain improvements
  • Water line improvements

Project Updates

The Town staff intends to provide updates on the happenings as much as it is available. Please remember that the information provided is what is available to staff via their team and other third parties and it is subject to change. Staff will strive to keep Trophy Club looking and functioning at its best while keeping its residents informed to the best of their abilities.

July 12, 2019:

Staff is working on a parking plan with the school district and coordination with USPS in regards to the temporary mailboxes. As soon as we have answers, an email will be provided. 

If you have not already done so, please contact Tommy Uzee to be included on his communication list.  TUzee@trophyclub.org or 682.237.2915

July 10, 2019

Town Hall Meeting held for the public to further explain project details, answer questions from the contractor and receive an anticipated schedule of activities.  Estimated project start date (Sundance Court) is July 22, 2019.
Town Hall Meeting Notice

June 28, 2019 - 2:00 PM

Precon meeting held between Town staff, Teague, Nall & Perkins (TNP) and Jackson Construction in which details and plans were reviewed and discussed.  Town Hall Meeting scheduled for July 10, 2019 at 7:00 PM for residents to hear from contractors and ask questions.  The sequence of construction at this time will take place with the following estimates in timing from the date of section start:

  • Sundance Court
         - Estimated substantial completion within 90 calendar days
         - Estimated final acceptance within 15 calendar days
  • Trophy Club Drive
         - Estimated substantial completion within 160 calendar days
         - Estimated final acceptance within 30 calendar days
  • Meadowbrook Lane
         - Estimated substantial completion within 100 calendar days
         - Estimated final acceptance within 15 calendar days

May 14, 2019 - 8:00 PM

Town Council approved a contract with Jackson Construction for work with the anticipated project start date of July 22, 2019.  The project will start with Sundance Court, followed by Trophy Club Drive, then Meadowbrook Lane.

April 17, 2019 - 1:00 PM

The latest schedule for the Trophy Club Drive, Sundance Court, and Meadowbrook Lane road construction has been accepted. The project is scheduled for commencement on June 3, 2019, and will begin with Sundance Court. This will prevent any confusion with the July 4, 2019 parade. Trophy Club Drive will commence on, or about, July 8, 2019.