ABOUT the Sound Wall Project


The Texas Department of Transportation (TxDOT) has started the SH 114 expansion project, which includes two sections of sound wall to help buffer highway traffic noise.  TxDOT plans to add an interior lane in both directions from Kirkwood to Trophy Lake Drive, and an interchange at SH 170 and Parrish Lane. The sound wall will be 14’ tall and stretch from Marshall Creek east to The Village Shopping Center and from the creek on the east side of Beck’s property at SH 114 at Trophy Club Drive to Lake Cities Church of Christ. 

      

Project Updates


The Town staff intends to provide updates on the happenings as much as it is available.  Please remember that the information provided is what is available to staff via their team and other third parties and it is subject to change.  Staff will strive to keep Trophy Club looking and functioning at its best while keeping its residents informed to the best of their abilities.

8/17/2018 — 4:00 PM
No new updated schedule received from TxDot at this time, painting/sealing has begun on the east wall, main supports have continued on the west wall.

7/13/2018 — 2:00 PM
The following update was provided from Mike Glisson at the Denton Area TxDOT office:

The final drill shafts at wall#1 will be completed by the end of the next week (July 20th, 2018).  Construction of sound wall #1(western wall) continues with setting columns, grading, and setting panels.  Sound wall #2 is near completion with setting the top wall panel caps, painting, removing dirt fill (work road), and placement of SOD.   The project is making progress and is scheduled for full completion by November 2018. If you have any questions, feel free to contact me.

7/12/2018 — 2:00 PM
Staff is currently waiting to hear back from TxDOT with an update on the Sound Wall construction progress and schedule. For those interested in the background of this project, please find attached the documentation from TxDOT as to the Traffic Noise Technical Report and the Guidelines for Analysis and Batement of Roadway Traffic Noise.  

  

If you have any questions regarding the sound wall, please contact James “Mike” Glisson at the Denton Area TxDOT office (940) 387-1414

7/06/2018 — 8:00 AM
Construction on the east wall has all panels on site and the remaining panels should be in place soon. The west wall is completing piers and main setting.  

6/29/2018 — 1:30 PM
Panels continue to be set between mainstays and production remains steady. Very few panels are left to install on the east wall and columns continue to rise out of the ground to the west.

6/22/2018 — 6:30 PM
Panel installation is progressing on the sound wall project on the east wall. The west wall continues to set pier steel and columns.


6/15/2018 — 3:45 PM
The sound wall along SH114 is progressing rapidly. All of the vertical supports appear to be completed and panels are now being put into place.
 
5/29/2018 — 3:00 PM
The TxDOT Project Manager responsible for the sound wall construction has provided the Town with the following update.
  • Wall 1 (west wall) – Drill shafts are 50% complete.
  • Wall 2 (east wall) – Currently pouring mow strip.  Columns are complete.  We will be setting panels by mid-June. 
If you have any questions regarding the sound wall, please contact James “Mike” Glisson at the Denton Area TxDot office (940) 387-1414

5/02/2018 — 9:00 AM
The TxDOT Project Manager responsible for the sound wall construction has provided the Town with the following update.

  • Wall 1 (west wall) – about 10% complete on drill shafts. Another 90% to go.

  • Wall 2 (east wall) – all shafts are in except for one. Columns are being placed and will be filled with concrete that has to cure before setting the wall panels.

If you have any questions regarding the sound wall, please contact James “Mike” Glisson at the Denton Area TxDot office (940) 387-1414